MariaDB/Primary switchover

From Wikitech
Jump to navigation Jump to search

Prerequisites shared for all sections

(The following points apply to planned switchovers only, skip directly to section links below when responding to an incident)

  • Create a switchover task (see previous tasks) (We have a script to generate the task content)
  • Schedule the switchover for one of the two weekly maintenance windows (check other open tasks and the deployment calendar for possible conflicts):
    • Tuesday at 6:00 AM UTC
    • Thursday at 6:00 AM UTC
  • Obtain explicit availability confirmation (over any channel) from at least one other person and add them to the task using the "Other assignee" field
  • Send a calendar invite to sre-data-persistence@
  • Add a user-notice Phabricator tag to the task for CRT's visibility