Lets figure out what steps we want to take in order to integrate the Foundry switch.

Here is a starting point:

  • Connect up all access switches and routers to the Foundry.
  • Move srv1-30 and db's onto the first patch.
  • Do away with the netgear.
  • Move any other servers we want on the Foundry from csw1 to the second patch.
  • Disconnect the fiber from csw1 and route a new fiber to the foundry.
  • Once the first fiber uplink is established, do the same with the other one.
  • Use remaining cisco's as access switches and backup routers.