Lets figure out what steps we want to take in order to integrate the Foundry switch.
Here is a starting point:
- Connect up all access switches and routers to the Foundry.
- Move srv1-30 and db's onto the first patch.
- Do away with the netgear.
- Move any other servers we want on the Foundry from csw1 to the second patch.
- Disconnect the fiber from csw1 and route a new fiber to the foundry.
- Once the first fiber uplink is established, do the same with the other one.
- Use remaining cisco's as access switches and backup routers.